Caldwell Breaks Ground On Fire Station 4 As Response Times Hit 18 Minutes
Caldwell broke ground on Fire Station 4 near Lake Avenue and Karcher Road to fix slow response times in the fast-growing southeast.

Caldwell Fire crews turned dirt Thursday on the city's fourth fire station, a project intended to improve response times for southeast residents who say help has taken as long as 18 minutes to arrive. The new facility will rise near Lake Avenue and Karcher Road, placing an engine company directly in a corner of the city that's filling up fast with new homes, businesses and traffic.
City leaders, firefighters and community members gathered for the groundbreaking on Thursday, according to KBOI. As reported by KIVI, work began that day on the project, which is designed to put an engine crew directly in southeast Caldwell rather than relying on stations farther away. Fire Station 4 is set to open in November 2027, per KIVI's reporting, though KBOI's account frames the completion target as mid-November 2027.
The gap between the department's goal and current reality is stark. A call to southeast Caldwell can currently take 12 minutes, according to KIVI, well above the four-minute response goal the new station is meant to achieve. Cedar Crossing subdivision resident Rick Read told the station it's been like 15, 18 minutes in his neighborhood, and KBOI reports a Cedar Crossing resident separately described Station 2 as 12 to 15 minutes away, sometimes 20 minutes away.
Residents Describe Long Waits for Help
For families living in the subdivision, the stakes aren't abstract. A Cedar Crossing resident told KBOI that having first responders close to the community matters in a fire or medical emergency, a sentiment that echoes the frustration Read voiced to KIVI about minutes stretching into double digits while waiting for sirens to arrive. Caldwell Fire Chief Bryan Daniels told KBOI that the fire service promises 911 callers a fast response, and said the groundbreaking advances that promise.
The new station will include a kitchen and gym and is planned at roughly 8,200 square feet, per KBOI. It's expected to help the Caldwell Fire Department serve the surrounding neighborhoods that have sprung up around Lake Avenue and Karcher Road, an area seeing both commercial development and new subdivisions, KIVI reported in earlier coverage of the department's expansion plans.
A City Straining Under Its Own Growth
The numbers behind the project point to a department under mounting pressure. Caldwell's fire department currently operates four stations, three in the city and one rural, according to the department's FY2026 budget presentation posted by the City of Caldwell, which also reported more than 8,200 annual calls handled by 22 on-duty firefighters per day. That same budget document projected call volume would exceed 9,200 the following year, citing increasing emergency calls, expanding neighborhoods and higher service expectations as the city grows.
Fire Chief Bryan Daniels offered a slightly different set of figures to Idaho News, saying the department handled 8,200 calls this year and expects about 9,000 next year, adding that call volume has consistently increased over the last several years. Separately, the Idaho Statesman has reported that Caldwell's population has grown just under 30% since 2020, a pace that's left firefighters responding to high call volumes across an expanding city.
Bond Money Funds Three Facilities
Fire Station 4 is one piece of a larger, voter-approved construction push. The entire program carries a $20 million budget, with $17.3 million coming from the approved bond measure, according to the Idaho Business Review. That bond is also funding a rebuild of Fire Station 1 and a new fire administration building, with CORE Construction handling all three builds and Pivot North Architecture providing the designs.
The department's FY2026 budget proposal also notes that funding for new growth, including Station 4, is eligible for impact fees, according to the city's own presentation. Looking further ahead, the department's FY2027 priorities include planning a fifth fire station in the northeast Caldwell corridor, the city's budget documents show, suggesting Station 4 is a step in a longer expansion rather than a final fix.
Staffing Questions
How the new station gets staffed remains a bit murky. KIVI has reported that Caldwell approved six new firefighters in 2026 to help staff the facility, leaving the final staffing arrangement unclear.