Eastbound I-696 to begin reopening this weekend

Barring weather or construction delays, eastbound I-696 between M-10 and I-75 is expected to begin reopening Saturday, Nov. 21, and be fully open by 5 a.m. Monday, Nov. 23, marking a major milestone in the $250 million…

59 WMMI Staff18 November 2026 at 20:57 UTC2 min read
Eastbound I-696 to begin reopening this weekend

Barring weather or construction delays, eastbound I-696 between M-10 and I-75 is expected to begin reopening Saturday, Nov. 21, and be fully open by 5 a.m. Monday, Nov. 23, marking a major milestone in the $250 million Restore the Reuther project in Oakland County.

Eastbound I-696 first closed in March 2025 between Lahser Road in Southfield and I-75 in Royal Oak. The Michigan Department of Transportation said crews are wrapping up pavement markings, signs and other finishing work before reopening the freeway.

Before the full reopening, eastbound I-696 will be reduced to one lane from Orchard Lake Road to M-10 from 8 a.m. to 5 p.m. Saturday, Nov. 21, while crews remove and replace pavement markings approaching the current detour route, according to an MDOT news release.

During that work, the eastbound I-696 ramp to southbound M-10, US-24 and Lahser Road will be closed, along with southbound M-10 at I-696. Once that work progresses east of M-10, eastbound I-696 will reopen to I-75, according to MDOT.

More: Why did 2 horses board a Detroit bus? See footage, hear from owner

The freeway and its associated eastbound entrance and exit ramps are scheduled to be open by 5 a.m. Monday, according to DrivingOakland, ending the long-running eastbound detour between M-10 and I-75 associated with the freeway's reconstruction. One exception is the southbound Telegraph Road ramp to southbound M-10, which will remain closed until about mid-December.

More: Ford CFO: Path to EV profitability could run through new UEV platform

The $250 million Restore the Reuther project has included replacing eight miles of pavement, improving 60 bridges and rebuilding the Church Street plaza.

The Church Street bridge over I-696 will reopen along with one pedestrian crossing, according to MDOT. Work on the plaza will continue in 2027 to complete the park and parking lot.

Work on the final phase of the project will resume in early 2027 between I-75 and Dequindre Road with pavement improvements, roadway rebuilding, bridge improvements and drainage work. I-696 is expected to remain open during that time.